Rawson Homes Chifley 37 - Metro Facade

Week Three – Plumbing, Piering and Formwork

There was a fair amount of action on site this week! We started the week with our site having some further cutting to shape it for our drop edge beams and the plumbing for the slab being laid. Then we had our piering completed and our formwork started, the form work gave us an even better idea of how the house was going to sit on the block. We also got a delivery of our

Week Two – Rock Removal

Week Two was a bit of a slow week but there was still progress! We saw the site fence and porta-loo delivered as well as the rock removed from the front of the site. It is really beginning to look like real construction site now with the site fence and signage. Next week the slab preparation will begin with the plumbing and form work.

Week One – Site Preparation

Week One went fairly quickly! We were greeted by a email from our site supervisor giving us a heads up that we’d see some action on site this week. The block was booked in for the rite of passage when building a new home, the porta-loo and site fence. Also the site was booked to be cut this week too. Our site was cut on Tuesday, what a difference it made. They hit some rock

Top