There was a fair amount of action on site this week! We started the week with our site having some further cutting to shape it for our drop edge beams and the plumbing for the slab being laid. Then we had our piering completed and our formwork started, the form work gave us an even better idea of how the house was going to sit on the block. We also got a delivery of our waffle pods and steel reinforcement.