Well, week six brought the start of our Frame construction. Unfortunately due to the rain setting in later in the week the frame couldn’t be completed.
The ground floor went up on Monday, the garage wall and the rear of the ground floor is still unfinished and the steel posts still need to be installed.
The first floor went up on Wednesday and Thursday, there is still quite a bit to be completed up there but if we get some good weather next week it shouldn’t take more than a day or two to complete!
Our site supervisor has told us that the plumbing rough in is planned for next week (Week 7). Hopefully that and the frame is completed by the end of the week. I wonder if we’ll be able to fly the drone in to get some photos, haha.
GROUND FLOOR






FIRST FLOOR