4 October 2017
Looks like it is getting really close now.
30 July 2017
Olivia Place is complete! Now we wait for Ryan Place and all the things that come with land registration…
3 June 2017
The road is almost complete, we’ve also had gas installed which was a nice surprise.
27 May 2017
Over the past few months the plumbing has been completely torn up including half of our new kerb. We’re back at the same stage we were at in February. The plumbing is finished and the kerb is complete. We’ve now got one section of road laid.
During this time utilities have been laid including electricity, water and telecom. We’ve also got most of the foot path completed.
5 February 2017
Road base completed and the kerb has been installed, there is now form work for some of the sections of road. At this point we become aware that the original plumbers did the wrong thing and all the plumbing needs to be redone.
14 November 2016
The road base is now laid for Olivia Place
29 October 2017
More plumbing and excavation work
22 October 2016
More plumbing and excavation work
16 October 2016
Excavation work and the beginning of the failed stormwater plumbing
9 October 2016
More excavation work
2 October 2016
The excavation work has begun for Olivia Place and the new turning head on Ryan Place
24 September 2016
Remediation work now completed
10 September 2016
Remediation work still being completed
27 August 2016
At this date all the lots have just been sold and the developer is starting some remediation work on some of the land to the north where the old asbestos work sheds sat.